Investment Costs
The investment cost for a PT plant depends on the thermal storage and the capacity factor. The cost for aan PT plant are:
Thermal storage |
Capacity factor |
Costs in USD |
No |
20-25% |
4,600-7,100/kW |
4-6,5 hours |
>40% |
7,300-91,00/kW |
The costs of a 50 MW PT plant with a storage capacity of 7.5 hours has an estimated cost of USD 364 million or 7280/kW. The costs can be broken down in to multiple elements:
- The solar field (510,000 m2) is 38,5% of the costs
- Support structure (10,7%)
- Receivers (7,1%)
- Mirrors (6,4%)
- Heat transfer system (5,4%)
- Fluid (2,1%)
- Thermal storage system is 10,5% of the costs
- Salt (5%)
- Storage tanks (2%)
- Power block, balance of plant and grid connections account for 14% of the costs
- Labor for 500 persons for the plan construction is 17% of the costs
- EPC and financing costs are 19,5% of the costs