Investment Costs

The investment cost for a PT plant depends on the thermal storage and the capacity factor. The cost for aan PT plant are:

Thermal storage

Capacity factor

Costs in USD

No

20-25%

4,600-7,100/kW

4-6,5 hours

>40%

7,300-91,00/kW   


The costs of a 50 MW PT plant with a storage capacity of 7.5 hours has an estimated cost of USD 364 million or 7280/kW. The costs can be broken down in to multiple elements:

  • The solar field (510,000 m2) is 38,5% of the costs
    • Support structure (10,7%)
    • Receivers (7,1%)
    • Mirrors (6,4%)
    • Heat transfer system (5,4%)
    • Fluid (2,1%)
  • Thermal storage system is 10,5% of the costs
    • Salt (5%)
    • Storage tanks (2%)
  • Power block, balance of plant and grid connections account for 14% of the costs
  • Labor for 500 persons for the plan construction is 17% of the costs
  • EPC and financing costs are 19,5% of the costs